Bridgewell Construction Ltd in material breach of £1.84m community buildings refurbishment contract (due Oct 2024; none of 3 buildings complete by Mar 2025). £1.02m paid (55%) vs ~40% programme progress. LADs accruing £1,500/week/building (£97,500 to date). Recommends: issue JCT Default Notice (14 days to remedy), then terminate and engage replacement contractor; pursue LADs via adjudication; recover £184k performance bond.